Pictures of Recent Work

January 12, 2017

January 12, 2017

January 12, 2017

January 12, 2017

January 12, 2017

Site Demobilization February to April, 2015

De-mobilization from site on Feb. 23, 2015.

De-mobilization from site on Feb. 23, 2015.

De-mobilization from site on March 29, 2015.

De-mobilization from site on March 29, 2015.

De-mobilization from site on March 30, 2015.

De-mobilization from site on March 30, 2015.

De-mobilization from site on April 17, 2015.

De-mobilization from site on April 17, 2015.

De-mobilization from site on April 20, 2015.

De-mobilization from site on April 20, 2015.

De-mobilization from site on April 29, 2015.

De-mobilization from site on April 29, 2015.

In-situ Thermal Remediation Continues

Frac tank (mobile steel storage tank) for extra discharge water.

Frac tank (mobile steel storage tank) for extra discharge water.

Repairing the discharge pump on July 31st.

Repairing the discharge pump on July 31st.

Repairs completed to the oxidizer in late August.

Repairs completed to the oxidizer in late August.

July Activities at SRSNE

Wellfield piping.

Wellfield piping.

Decanting Light Non-Aqueous Phase Liquids (LNAPL) from the oil/water separator on 7/16/2014

Decanting Light Non-Aqueous Phase Liquids (LNAPL) from the oil/water separator on 7/16/2014

Placing the Geoprobe, using a crane, onto the wellfield to collect soil samples in late July.

Placing the Geoprobe, using a crane, onto the wellfield to collect soil samples in late July.

Geoprobe drilling through the concrete cap for sampling.

Geoprobe drilling through the concrete cap for sampling.

20140728-DSC02850-cooling hot soil samples

Cooling the hot soil samples for logging and containerizing for shipment to laboratory.

ISTR System Operations and Maintenance

20140617-DSC02725-collecting hot gw samples

Hot Groundwater Sampling

20140612-DSC02718-maintenance of the wellfield

Maintenance of the well field on June 12th.

20140606-DSC02707-system maintenance

Maintenance of the treatment system on June 6th

 

2014 Comprehensive Groundwater Sampling

20140610-DSC02710-annual GW sampling

2014 comprehensive groundwater sampling took place June 9th to June 13th, 2014.

In-Situ Thermal Remediation Begins

In-Situ Thermal Remediation Begins on May 15, 2014

In-Situ Thermal Remediation Begins on May 15, 2014

Start-Up to Begin Soon

Start-up soon!

Start-up soon!

Oblique Areial of ISTR from April 29, 2014

Oblique Aerial of ISTR from April 29, 2014

February 2014 Photos

Cabling connections to electrical power controllers on Feb 7, 2014

Cabling connections to electrical power controllers on Feb 7, 2014

A snow covered view from SW looking NE on Feb. 10, 2014

A snow covered view from SW looking NE on Feb. 10, 2014

Kicking off the New Year

Vapor Treatment System Construction on Jan. 7, 2014

Vapor Treatment System Construction on Jan. 7, 2014

Jan. 21, 2014

Jan. 21, 2014

December 2013

Monitoring Well (#4 or 7)

Monitoring Well (#4 of 7)

Vapor monitoring wells on Dec. 13, 2013
Vapor extraction wells on Dec. 13, 2013

View from SW on Dec. 31, 2013.

Piping and cabling installation. View from SW on Dec. 31, 2013.

 

November Photos

View from SW looking toward NE on Nov. 15, 2013.

View from SW looking toward NE on Nov. 15, 2013.

Start of cabling to well heads Nov. 19, 2013.

Start of cabling to well heads Nov. 19, 2013.

 

 

 

Cap Installation Oct-Nov, 2013

Start of cap installation on Oct. 1, 2013.

Start of cap installation on Oct. 1, 2013.

Cap installation Oct. 14, 2013

Cap installation Oct. 14, 2013

Applying sealant to cap on Nov. 4, 2013

Applying sealant to cap on Nov. 4, 2013

Well field completed - Nov. 12, 2013

Well field completed – Nov. 12, 2013

Open House 2013

de maximis Project Coordinator discussing the site remediation progress with a group from UCONN and Middlesex Community College

de maximis Project Coordinator discussing the site remediation progress with a group of students from UCONN and Middlesex Community College.

Many topics were discussed, such as thermal treatment, groundwater monitoring, and future work. For more details see the Documents and Links Page for “Open House 2013” Posters and Briefing Book.

 

Bedrock Core

8-8-13_bedrock core

John (Cascade Drilling) and Garrett (TerraTherm) prepare a core for determining bedrock.

8-8-13

 

Installed to date:

HO-440 (74%)

VEW-428 (78%)

TMP-60 (62%)

PMP-42 (66%)

ISTR- 3 (43%)

 

 

Drilling Status Update

8-6-13

 

Installed to date:

430 (73%)  Heater Wells (HO)

419 (76%) Vapor Extraction Wells (VEW)

57 (59%) Temperature Monitoring Points (TMP)

PMP- 40 (63%)  Pressure Monitoring Points (PMP)

2 (29%) In-situ Thermal Remediation (ISTR)

Site Photo July 30,2013

7-30-13

Installed to date:

415 (70%) Heater Wells (HO)

403 (73%) Vapor Extraction Wells (VEW)

54 (56%)  Temperature Monitoring Points (TMP)

38 (59%) Pressure Monitoring Points (PMP)

2 (29%) In-situ Thermal Remediation (ISTR)

 

 

Status Update

 

6-27-13_pwrpnt

Installed to date: 321 (54%)Heater Wells (HO), 312 (57%) Vapor Extraction Wells (VEW), 40 (41%) Temperature Monitoring Points (TMP), and 28 (44%) Pressure Monitoring Points (PMP).

Status Update of ISTR Well Installation

6-20-13_pwrpnt

 

Installed to date: 283 (48%) Heater Wells (HO), 280 (51%) Vapor Extraction Wells (VEW), 31 (32%) Temperature Monitoring Points (TMP), and 24 (38%) Pressure Monitoring Points (PMP).

Drilling Progress Continues at SRSNE

 

6-3-13-26-3-13-1Views from southwest looking to the northeast.

It has now been over one month of drilling and installation of the in-situ thermal remediation wells. The team is working hard and doing a great job and currently on schedule. Again, one can see the well pairs, which consist of an electrically powered heater well and a vapor extraction well.  Installed to date: 201 Heater Wells (HO), 199 Vapor Extraction Wells (VEW), 25 Temperature Monitoring Points (TMP), and 20 Pressure Monitoring Points (PMP).

Drilling Continues

5-13-13-1

 

View from southwest looking to the northeast.

Drilling continues. The vapor extraction wells are located approximately 3 feet from the electrically powered heater wells. In addition the team is installing Temperature Monitoring Points and Pressure Monitoring Points. To date we’ve installed: 109 Heater Wells (HO), 105 Vapor Extraction Wells (VEW), 9 Temperature Monitoring Points (TMP), and 9 Pressure Monitoring Points (PMP). Also, note the air monitor in the foreground.

In-situ Thermal Remediation – Drilling Begins

 

4-26-13-24-26-13-1

Views from southwest looking to the northeast.

 

Boart Longyear begins drilling in-situ thermal remediation (ISTR) wells, which consist of electrically powered heater wells and vapor extraction wells. Installed to date: 24 Heater Wells (HO), 24 Vapor Extraction Wells (VEW), 1 Temperature Monitoring Point (TMP), and 1 Pressure Monitoring Point (PMP).

In-situ Thermal Remediation System Proposed Wellfield

4-23-13-1

View from northeast looking to the southwest showing the proposed in-situ thermal remediation (ISTR) wellfield and thermal treatment zone.