Drilling Progress Continues at SRSNE

Drilling Progress Continues at SRSNE

 

6-3-13-26-3-13-1Views from southwest looking to the northeast.

It has now been over one month of drilling and installation of the in-situ thermal remediation wells. The team is working hard and doing a great job and currently on schedule. Again, one can see the well pairs, which consist of an electrically powered heater well and a vapor extraction well.  Installed to date: 201 Heater Wells (HO), 199 Vapor Extraction Wells (VEW), 25 Temperature Monitoring Points (TMP), and 20 Pressure Monitoring Points (PMP).